The Kitchen Studio

Gungiah

Installation Completion Tracker

Fitter returns

Monday, 9 November 2026

Provisional completion target

Wednesday, 25 November 2026

Provisional — subject to confirmation of outstanding factory deliveries.

Fitting and snagging planned for 9–20 November. 23–25 November allowed for remaining fitting and final snagging.

Latest update from TKS

Last updated Tue, 03 Nov 2026, 12:00 SAST

The fitter is scheduled to return on Monday, 9 November. The remaining parts for the TV lounge and Bedrooms 2 and 3 are expected that week. We’re confirming factory delivery dates for the additional items and will update this tracker as those dates are confirmed.

Outstanding Original Scope3 open · 0 complete

TV lounge

Expected on truck

Remaining parts to be delivered and fitted.

Expected delivery
Week of 9 November
Planned fitting
To be confirmed

Remaining parts expected during the week of 9 November. Fitting to follow once received; exact dates to be confirmed.

Bedroom 2

Expected on truck

Ceiling closure panels.

Expected delivery
Week of 9 November
Planned fitting
To be confirmed

Panels expected on the truck during the week of 9 November. Fitting to follow once received.

Bedroom 3

Expected on truck

Two missing fronts.

Expected delivery
Week of 9 November
Planned fitting
To be confirmed

Fronts expected on the truck during the week of 9 November. Fitting to follow once received.

Additional Work4 open · 0 complete

Main vanity

Awaiting factory confirmation

Supply and fit.

Expected delivery
To be confirmed
Planned fitting
To be confirmed

Ordered 13 October. Awaiting factory delivery confirmation.

Main bedroom dresser — additional work

Awaiting factory confirmation

Additional dresser work (separate from the completed dresser).

Expected delivery
To be confirmed
Planned fitting
To be confirmed

Ordered 13 October. Awaiting factory delivery confirmation.

Kitchen island

Awaiting factory confirmation

Supply and fit.

Expected delivery
To be confirmed
Planned fitting
To be confirmed

Ordered 13 October. Awaiting factory delivery confirmation.

Door frames

Awaiting factory confirmation

Lamination outstanding.

Expected delivery
To be confirmed
Planned fitting
To be confirmed

Lamination outstanding. Delivery and fitting dates to be confirmed.

Snagging1 open · 0 complete

General snagging

Scheduled for fitting

Snags to be identified and closed out.

Expected delivery
To be confirmed
Planned fitting
Monday, 9 November 2026

Snagging planned from the fitter’s return on 9 November. Individual snags will be listed here as they are identified.

Completed Installation0 open · 10 complete